Four Ferndale (UK) turbines started production

The first four turbines at our Ferndale Wind Farm in the Rhondda Valleys in Wales have started to produce electricity during their 240 hours trial run. The mechanical completion inspection on these turbines has been carried out last week.

The other four turbines are still under construction and comissioning. These remaining turbines will start to produce at the end of May.